Attachment A
|
1. |
Recommendation of MSHCP Advisory Committee: |
|
Approve the draft
Implementation Outline with the understanding that the document
is a work in progress and will require additional discussions
to resolve outstanding issues.
|
|
County staff’s proposed alternative: |
|
a) Approve in concept an implementation program
predicated on land acquisition as the primary tool to achieve MSHCP conservation
objectives. Such land acquisitions would occur with willing sellers pursuant to
Section 10.7 of the Western Riverside Multiple Species Habitat
Conservation Planning Agreement.
b) Refer the MSHCP Advisory Committee’s
Funding and Implementation Outline to staff for further examination
of policy and legal issues with County Counsel, USFWS, CDFG, and
all western Riverside cities and direct staff to report back to
the Board in 30 days;
|
2. |
Recommendation of MSHCP Advisory Committee: |
a) |
That, for purposes of defining the project description
for the MSHCP and defining the preferred project in the joint
CEQA/NEPA document, the consultants analyze Alternative 1 consistent
with the proposed Funding and Implementation Outline. Additionally, the
environmental document may include an analysis of those alternatives
considered in the October 4, 2000 Alternatives Development Document.
Stakeholders reserve the opportunity to comment on other alternatives
that might emerge in the course of the environmental review process.
|
b) |
That the MSHCP environmental document evaluate a range
of alternatives for the San Jacinto River.
|
|
County staff’s proposed alternative: |
|
Approve Alternative
1 as the project for purposes of preparing the draft MSHCP and
issuing a NOP in accordance with CEQA;
|
3. |
Direct
the project consultant to proceed with a conservation analysis
that contemplates participation by all 14 western Riverside County
cities but direct staff to continue discussions with Lake Elsinore
to ascertain the city’s preferred conservation approach and report
back to the Board in 30 days; and,
|
4. |
Approve in concept the attached Parks and Open
Space Concept Report as the basis for a public access plan and
direct the RCIP Consultant to seek input from the MSHCP and
General Plan Advisory Committees. Consultant will incorporate
committee comments and comments received from the County Parks
District and TLMA staff into a final product by April 15, 2001.
|
BACKGROUND: On December 19, 2000 your Board directed
staff and the MSHCP consultant to proceed with the conservation
analysis for Alternative 1 as described in the October 4, 2000
Alternatives Development Document and incorporate the recommendations
of the MSHCP Advisory Committee and–to the extent feasible–written
comments received by the USFWS, CDFG, WRCOG, individual Advisory
Committee members and other interested parties.
It was understood that, if the Committee could not achieve
agreement on a preferred alternative by March 1, 2001, the County
would have to either delay the project, thereby resulting in impacts
to the RCIP schedule and budget, or obtain Board direction to
proceed with developing the environmental documentation pursuant
to CEQA and NEPA.
Alternative 1 considers a conservation scenario that
would protect approximately 164 species and provide for the viability
and recovery of Western Riverside County ecosystems, habitats, and
species through a 510,000 acre network of reserves and linkages.
Of that 510,000 acres, approximately 350,000 acres are
already within public ownership and 153,202 acres would be acquired
or otherwise conserved through negotiations with private property
owners. This alternative is based upon the
draft Western Riverside County Multiple Species Habitat Planning
Agreement (Planning Agreement) and the broad-based biological
tenets of the state’s Natural Communities Conservation Planning
(NCCP) Act.
|
A.
|
Funding and Implementation Program
|
|
Since December
19, 2000 representatives of the MSHCP Advisory Committee worked
together to develop a draft Funding and Implementation Outline
(Outline) for your consideration (Attachment B).
County staff, representatives of the U.S. Fish and Wildlife
Service (USFWS), and California Department of Fish and Game (CDFG)
provided initial input into this process.
Salient features of the Outline are listed below:
|
1. |
Local funding would be derived from a development mitigation
fee, development incentives, landfill tipping fee revenues, infrastructure
mitigation funds, and other funding sources with a fair share
land acquisition contribution by the state and federal governments.
|
2. |
Landowners shall be provided a pre-development conference
in which prospective subdivision and development projects shall
meet to confer on project design, incentives, and acquisition
alternatives. The purpose of this conference is
to allow for an opportunity whereby the County and the project
proponent apply MSHCP conservation criteria and where appropriate,
negotiate the parameters of conservation and/or acquisition, and
development.
|
3. |
A Conservation Planning Area (CPA) overlay that shall not
apply any new standards or criteria for land use but rather facilitate
information by which the County evaluates land for inclusion within
the MSHCP reserve system.
|
4. |
An incentive program designed to actively encourage, reward,
and compensate landowners within the CPA who conserve all or a
portion of their property consistent with the MSHCP.
|
5. |
Landowners shall be provided the opportunity to invoke
a conflict resolution process should there be an impasse between
the County and the property owner concerning the value of the
land necessary for conservation.
Such a process relies on condemnation as a potential final
outcome.
|
6. |
Safety nets and annual reviews. |
|
The MSHCP Advisory
Committee unanimously approved the draft Implementation Outline
during their March 1, 2001 meeting with the understanding that
the document is a work in progress and will require additional
discussions to resolve several outstanding such as mitigation,
communication with cities, safety nets/assurances to resource
agencies, wetland/streambed protection, management, and funding
mechanisms.
Staff commends the dedicated efforts of MSHCP
Advisory Committee members to fashion the draft Implementation Outline.
However, there are issues that appear problematic and will
require further input from legal counsel and the Resource Agencies.
Preliminary comments expressed by staff, County Counsel, and the
Resource Agencies are identified below.
|
Staff Comments:
|
1. |
The Outline proposes an implementation program that relies
on condemnation (voluntary and involuntary) as a primary method
for resolving disputes concerning property value.
This is a departure from a fundamental tenant of the Planning
Agreement which states that land will be acquired from willing
sellers. Based on recent discussions in Washington, D.C., with
Interior Staff and lawmakers, a condemnation-based plan could
severely impact our ability to obtain state and federal support.
|
2. |
The MSHCP implementation program should encourage property
owners to offer their property for sale and negotiate terms that
are consistent with available funding and appraised value as determined
by local, state, and federal appraisal standards and acquisition
programs. Greater consideration should be
given to landowners who are willing to negotiate a mutually agreeable
acquisition strategy rather than to those who are pursuing condemnation
as a method to receive priority processing and pricing.
|
3. |
Despite the County’s aggressive campaign for funding that
resulted in recent state and federal conservation money coming
to Riverside County, there are limited dollars immediately available
to acquire all the land that could be submitted for conflict resolution.
Therefore, consideration should be given to a phased acquisition
program for those projects that utilize the proposed conflict
resolution process. Either payment over time or an allowance
should be made for a specified time window in which to complete
acquisitions.
|
4. |
There appears to be a local preference for creating an
implementation mechanism that utilizes land acquisition as the
primary tool to achieve the conservation objectives of the MSHCP
rather than deriving conservation through land use policy.
|
5. |
Standard project design requirements should be factored
into the habitat acquisition negotiation process (see flow chart
in Attachment B). Under normal development conditions, development
projects might be required to set aside land or provide a certain amount
of open space mitigation in conjunction with otherwise lawful development
pursuant to existing local, state, or federal regulations.
While conservation of that land may be considered during
the habitat acquisition negotiation process, the expectation should
not be that a property owner/developer would be compensated for
lands that would otherwise be restricted if the project was outside
of the Conservation Planning Area.
|
6. |
Staff recognizes that there is a desire to avoid new regulatory
requirements but new laws are enacted regularly. While the plan would seek
to minimize the effects of new regulations to the greatest extent possible,
we should be mindful of the instances where the conservation benefits
of such regulations exceed the impacts and thus be open to utilizing
such regulations where practicable. Controls based on wetlands, flood management,
steep slopes, seismic faults, and other conditions covered by existing law,
regulations, or by policies relative to public health and safety
issues can help to implement the MSHCP without adding unreasonable
burden to property owners/developers. To that end, the Implementation Outline
should recognize the use of minimally intrusive land use policies that would
otherwise apply to project development in Riverside County.
|
7. |
Essential to obtaining state and federal incidental take
permits is the ability of the County and other implementing jurisdictions
to provide assurances that the reserve system proposed in the
MSHCP can be achieved. Since the County is pursuing a criteria-based plan
that provides for a 153,202 acre reserve system to be assembled within a
Conservation Planning Area of approximately 250,000 acres, assurances would
take the form of “safety nets.” Safety nets are measurable/quantifiable
conditions linked to MSHCP criteria that—if not achieved—trigger incremental
increases in certain pressure mechanisms designed to achieve MSHCP compliance.
Safety nets and their associated triggering mechanisms will need to be defined
in the coming months. However, it will be easier for all parties if they are
designed around a series of steps that could be taken short of revoking the
incidental take permits.
|
8. |
MSHCP assurance mechanisms should include project-level
review pursuant to the California Environmental Quality Act (CEQA).
If CEQA analysis discloses that approval of a project would trigger a
MSHCP safety net, then the Board would need to make an overriding finding.
If--in the opinion of the Resource Agencies–such an action precluded
reserve assembly, then the agencies could revoke the incidental take permits.
|
9. |
The MSHCP must be acceptable to the Regulatory Agencies
and legally defensible. This does not imply that the County should stop
short of proposing our locally preferred implementation strategy.
However, we may approach a point at which the MSHCP would
require revisions to reflect vital input from the state and federal
permitting agencies. Preliminary remarks from the USFWS are provided below.
|
Initial Concerns Expressed by County Counsel:
|
1. |
The conflict resolution process appears to be problematic
as the process relies quite heavily on eminent domain proceedings
to determine the cost of land should there be an impasse between
the County and the landowner with respect to land values. As a result
of the eminent domain process, the cost of acquiring land may increase
substantially due to attorneys’ fees, lengthy trials, jury decisions, etc.
Should this process be overused early in the implementation program, the
County’s General Fund monies could be depleted and its ability to fund the
MSHCP jeopardized. Eminent domain should be a tool of last resort, used
sparingly, and only at the County’s discretion. In short, the conflict resolution
process could have serious unintended consequences.
|
2. |
If a landowner chose to obtain their own ESA permits outside
the scope of the MSHCP as provided in the Outline, it is unclear
how the County would have the authority to require compliance
with the MSHCP.
|
3. |
There are significant legal implications associated with
identifying all landowners and other land development project
proponents within the MSHCP boundary as third party beneficiaries
of the incidental take permits.
|
4. |
Given the fact that the latest version of the draft Outline
was submitted to County Counsel on March 9, 2001, County Counsel
requests additional time to assess more fully the legal implications
of the proposed implementation program.
|
Initial Concerns Expressed by the USFWS and CDFG:
|
1. |
The conflict resolution process requires additional discussion
and legal review, specifically the issue of condemnation. USFWS staff
indicated that condemnation should not be part of the MSHCP Implementation
Agreement. CDFG staff noted that a court might not judge for appraised
value, yet state and federal standards only provide for acquisitions
at appraised value.
|
2. |
Quantifiable and measurable safety nets and triggers need
to be refined in conjunction with MSHCP criteria.
|
3. |
Monitoring of preservation and loss should occur outside
as well as inside the CPAs.
|
4. |
The MSHCP implementation program must provide assurances
with respect to funding and plan development/reserve assembly.
|
5. |
Additional clarification is needed concerning the mechanism
that would provide greater certainty concerning how the plan is
implemented (e.g. through policy or through ordinance). Although
there was general agreement amongst the MSHCP Funding and Implementation
Subcommittee members that the MSHCP could be adopted through ordinance,
more discussion is needed to determine the nature of such an ordinance.
|
6. |
More investigation is required to determine if Safe Harbor
agreements and deed restrictions provide long-term conservation
assurances.
|
7. |
USFWS and CDFG staff have indicated that they would not
seek any change in tax law to achieve the objectives of the MSHCP. They
recommended that Section 7 (g) (vi) of the Outline be revised accordingly.
|
8. |
Further consideration of the issue of conservation of streams
and wetlands (Section 8 in Outline). While it is the intent of the MSHCP to
cover take of wetland species, there is some expectation that the biological
functions of streams/wetlands outside the CPAs will continue as a result
of existing regulations (e.g. Army Corps processes). Resource agencies advise
that the plan needs to demonstrate an ability to maintain function of watersheds
such that persistence of covered species will be assured.
|
9. |
Agricultural coverage under the MSHCP requires additional
discussion. Resource agencies have expressed concern regarding the
statement that existing/ongoing agricultural activities would be
“automatically covered.” The MSHCP will be required to analyze
the impacts of agricultural activities (including use of herbicides
and pesticides) and provide for incidental take expected to occur
as a result of such activities. The plan must also address how agricultural
activities are enrolled in and/or covered by the MSHCP. Additional consideration
must be given to how new agricultural activities are covered by the MSHCP.
|
10. |
State and federal staff have indicated that their implementation
obligation should be represented in terms of acres rather that
dollars.
|
11. |
Requests were made by USFWS and CDFG staff that subsequent
versions of this document include items relating to MSHCP management
and monitoring, and city participation (e.g., mechanisms, costs,
adaptive management objectives).
|
B.
|
Definition of “the project” for purposes of the draft MSHCP
and CEQA Documentation
|
|
The County will be preparing a joint draft Environmental
Impact Report/Environmental Impact Statement (EIR/EIS) for the MSHCP
pursuant to the CEQA and National Environmental Policy Act (NEPA).
For purposes of CEQA, the County acts as the lead agency. Similarly, the
USFWS is considered the lead agency for purposes of NEPA. While the EIR/EIS
will evaluate a range of alternatives, Section 15082 of CEQA stipulates that--for
purposes of a Notice of Preparation (NOP)--the lead agency must
provide a description of a project to be analyzed in the EIR. In order to
maintain the production schedule established for the MSHCP and the RCIP,
the County must--at this time--identify “the project” and issue a NOP to
initiate the CEQA review process.
Federal regulations
stipulate that the draft EIS must identify the lead agency’s “preferred
alternative” if one exists (emphasis added). However, the final
EIS must identify the preferred alternative (40 C.F.R. 1502.14(e); Forty
Questions No. 4(b)). USFWS staff informed the County that they are not
prepared to identify the preferred alternative at this juncture.
During its March 1, 2001 meeting, the MSHCP Advisory
Committee offered the following recommendations:
|
1. |
That, for purposes of defining the project description
for the MSHCP and defining the preferred project in the joint
CEQA/NEPA document, the consultants analyze Alternative 1 consistent
with the proposed Funding and Implementation Outline. Additionally, the
environmental document may include an analysis of those alternatives
considered in the October 4, 2000 Alternatives Development Document.
Stakeholders reserve the opportunity to comment on other
alternatives that might emerge in the course of the environmental
review process.
Recommendation
passed with 11 members in favor; Andy Domenigoni (on behalf of
Cindy Domenigoni), Farm Bureau, Elsinore-Murrieta-Anza Resource
Conservation District, Lockheed Corporation, and the Riverside
County Property Owners Association against; and Ed Sauls abstaining.
|
2. |
That the MSHCP environmental document evaluate a range
of alternatives for the San Jacinto River.
Recommendation
passed with 14 members in favor; Sierra Club against; and Edison,
Elsinore-Murrieta-Anza Resource Conservation District, and Lockheed
Corporation abstaining.
|
C.
|
City Participation
|
|
Confirmation of city participation is integral to
further MSHCP development and conservation analyses.
The draft MSHCP must consider which jurisdictions would
be covered by the incidental take permits and how conservation
assurances could be achieved.
If DUDEK were
to prepare a MSHCP that contemplates the participation of all
14 western Riverside County cities, and one or more cities opted
out at a later date, then the County would have to revise the
MSHCP and re-run the conservation analysis to address the loss
of the subject jurisdiction(s). This could only be accomplished
at substantial cost to the County and would result in significant
disruption to the RCIP schedule.
Conversely, the County could proceed with MSHCP development,
giving direction to the consultant that a certain jurisdiction(s)
be excluded from further consideration due to irreconcilable
approaches to implementing the state and federal endangered species
acts. Should that jurisdiction(s) later decide to re-enter the
planning process and receive coverage under the MSHCP permits,
then the cost of revising the plan would fall to the jurisdiction(s).
At present, staff is aware of MSHCP concerns
expressed by the cities of Murrieta, San Jacinto, Perris, and Beaumont.
We are engaged in discussions with representatives of those
jurisdictions in an attempt to address their respective issues.
However, during a January 25, 2001 Lake Elsinore City council
meeting, council members expressed dismay with the species and
habitat conservation levels identified within their jurisdictional
boundaries. Ensuing discussion focused on the inequity of species and
habitat distribution, perceived impacts to the city’s economy,
and general dissatisfaction with the ESA.
Rather than participate in the County’s MSHCP, the Lake
Elsinore City Council indicated its preference for approving development
projects and conditioning them to pursue incidental take permits
directly from the USFWS and CDFG or pursue an independent habitat
conservation planning effort.
Staff intends to meet again with city officials
from Lake Elsinore to discuss conservation options. A
status report will be presented to the Board in 30 days.
|
D.
|
Public Access Plan
|
|
On March 22, 2000, your Board authorized a contract
amendment with Sverdrup to proceed with development of draft text and
maps for compatible integration of recreation/public use in reserve
areas for integration into the General Plan and the MSHCP.
On February 8, 2001, staff received the attached Parks
and Open Space Concept Report (Attachment C) which provides an
initial assessment of open space/urban edge, opportunity site
and opportunity access types, and potential cost reduction and
revenue generating concepts.
It is staff’s opinion that the report provides a
basis for a public access plan that would integrate with the MSHCP
and General Plan elements of the RCIP. However, the report requires
additional work. It should be reviewed by the MSHCP and General Plan
Advisory Committees and County Park and Open Space District staff.
The final report should be updated with comments from those
entities and TLMA staff.
|
E.
|
Conclusions
|
|
The MSHCP preparation
proceeds along a critical path. Today, it is important that the
County provide policy direction concerning a MSHCP implementation
program, “the project,” city participation, and public access in order that the
RCIP consultant team may proceed with developing the draft MSHCP
and initiate CEQA/NEPA review. Without such policy direction, we
run the risk of severely impacting time lines for the MSHCP, the
General Plan, and CETAP.
|
ATTACHMENT B
MSHCP ADVISORY COMMITTEE’S PROPOSED
FUNDING AND IMPLEMENTATION PROGRAM
|
ATTACHMENT C
DANGERMOND REPORT
|
(Top)
|